• English
    • العربية
  • العربية
  • Login
  • QU
  • QU Library
  •  Home
  • Communities & Collections
View Item 
  •   Qatar University Digital Hub
  • Qatar University Institutional Repository
  • Academic
  • Faculty Contributions
  • College of Engineering
  • Civil and Environmental Engineering
  • View Item
  • Qatar University Digital Hub
  • Qatar University Institutional Repository
  • Academic
  • Faculty Contributions
  • College of Engineering
  • Civil and Environmental Engineering
  • View Item
  •      
  •  
    JavaScript is disabled for your browser. Some features of this site may not work without it.

    Time Delay and Cost Overrun in Qatari Public Construction Projects

    Thumbnail
    View/Open
    Publisher version (You have accessOpen AccessIcon)
    Publisher version (Check access options)
    Check access options
    1-s2.0-S187770581633973X-main.pdf (169.4Kb)
    Date
    2016
    Author
    Senouci, Ahmed
    Ismail, Alaa
    Eldin, Neil
    Metadata
    Show full item record
    Abstract
    This paper investigated cost overruns and delays in Qatari public construction projects. An extensive review of regional and international publications was conducted to get a better understanding of the problem and the various methodologies that were used to analyze it. The data that was collected from Qatar public work authority ASHGHAL included 122 public road, building, and drainage projects. ANOVA method was used for data analysis and inference. A regression analysis was also conducted to establish the relationships between project contract prices and cost overruns and to develop prediction models for estimating cost overruns. Two linear regression models were developed for predicting cost overruns for building and drainage public projects, respectively. Cost overruns for building projects increased with contract prices. On the other hand, cost overruns for drainage projects decreased with increasing contract prices. A significant effort was spent in collecting data on cost overruns and delays in public construction projects. However, data confidentiality did allow the collection of enough data to ensure the robustness of the developed regression prediction models.
    DOI/handle
    http://dx.doi.org/10.1016/j.proeng.2016.11.632
    http://hdl.handle.net/10576/22663
    Collections
    • Civil and Environmental Engineering [‎862‎ items ]

    entitlement


    Qatar University Digital Hub is a digital collection operated and maintained by the Qatar University Library and supported by the ITS department

    Contact Us | Send Feedback
    Contact Us | Send Feedback | QU

     

     

    Home

    Submit your QU affiliated work

    Browse

    All of Digital Hub
      Communities & Collections Publication Date Author Title Subject Type Language Publisher
    This Collection
      Publication Date Author Title Subject Type Language Publisher

    My Account

    Login

    Statistics

    View Usage Statistics

    Qatar University Digital Hub is a digital collection operated and maintained by the Qatar University Library and supported by the ITS department

    Contact Us | Send Feedback
    Contact Us | Send Feedback | QU

     

     

    Video