تصفح Mechanical & Industrial Engineering حسب الموضوع "Scheduling"
السجلات المعروضة 1 -- 5 من 5
-
An exact algorithm for the single machine problem with unavailability periods
( Inderscience Publishers , 2015 , Article)We investigate the single machine scheduling problem with job release dates and due dates, and multiple planned unavailability time periods. This problem arises in the context of machine scheduling with planned preventive ... -
Exact methods for the quay crane scheduling problem when tasks are modeled at the single container level
( Elsevier Ltd , 2018 , Article)The scheduling of quay cranes (QCs) to minimize the handling time of a berthed vessel is one of the most important operations in container terminals as it impacts the terminal's overall productivity. In this paper, we ... -
Heuristic and Exact Algorithms for the Two-Machine Just in Time Job Shop Scheduling Problem
( Hindawi Limited , 2016 , Article)The problem addressed in this paper is the two-machine job shop scheduling problem when the objective is to minimize the total earliness and tardiness from a common due date (CDD) for a set of jobs when their weights equal ... -
New characteristics of optimal solutions for the two-machine flowshop problem with unlimited buffers
( Taylor and Francis Ltd. , 2019 , Article)The two-machine flowshop problem with unlimited buffers with the objective of minimising the makespan (F2||Cmax) is addressed. Johnson’s algorithm finds optimal solutions (permutations) to this problem, but are not necessarily ... -
Robust optimization for the discrete time-cost tradeoff problem with cost uncertainty
( Springer International Publishing , 2015 , Book chapter)Projects are subject to various sources of uncertainty that hamper reaching project targets; hence, it is crucial importance to use effective approaches to generate robust project schedules, which are less vulnerable to ...