• English
    • العربية
  • العربية
  • Login
  • QU
  • QU Library
  •  Home
  • Communities & Collections
View Item 
  •   Qatar University Digital Hub
  • Qatar University Institutional Repository
  • Academic
  • University Publications
  • QU Conference Proceedings
  • International Conference on Civil Infrastructure and Construction (CIC 2023)
  • Theme 1: Contemporary issues in Construction Engineering and Management
  • View Item
  • Qatar University Digital Hub
  • Qatar University Institutional Repository
  • Academic
  • University Publications
  • QU Conference Proceedings
  • International Conference on Civil Infrastructure and Construction (CIC 2023)
  • Theme 1: Contemporary issues in Construction Engineering and Management
  • View Item
  •      
  •  
    JavaScript is disabled for your browser. Some features of this site may not work without it.

    Focus on Lean Construction at Umm Lekhba (Landmark) Interchange

    Thumbnail
    View/Open
    012.pdf (1.133Mb)
    Date
    2023
    Author
    Halimeh, Nader
    Metadata
    Show full item record
    Abstract
    Umm Lekhba (Landmark) Interchange is the largest four level Interchange built in Doha-Qatar, which has 9 flyover bridges with 11 km in total length, constructed partly using 735 heavy precast concrete segments fabricated off-site, transported, and installed using heavy cranes and launching trusses with a minimum impact on the public traffic flow and on the shopping activities at the busiest interchange in Doha. The Lean Construction Institution-Qatar (LCI-Q) was established in October 2019, and the Lean Construction implementation became mandatory for all new projects of Ashghal in Qatar as of 2022, however the construction of Landmark Interchange was started in May 2017, and two of its flyover bridges were opened to traffic at the end of 2019. The contract of the Landmark project did not mandate implementation of Lean Construction but the contractor had implemented part of Lean Construction and BIM techniques at his own cost to overcome the challenges faced in the design and construction of the project, including consideration of using the Last Planner System, Organization/Standardization of the workplace, implementation of Just in Time concept, using a systematic procurement approach, utilization of Multi-layer subcontractors and consultants, etc. This paper will present briefly the construction of Landmark Bridges and discuss Lean implementation during the construction.
    URI
    https://doi.org/10.29117/cic.2023.0012
    DOI/handle
    http://hdl.handle.net/10576/47046
    Collections
    • Theme 1: Contemporary issues in Construction Engineering and Management [‎39‎ items ]

    entitlement


    Qatar University Digital Hub is a digital collection operated and maintained by the Qatar University Library and supported by the ITS department

    Contact Us | Send Feedback
    Contact Us | Send Feedback | QU

     

     

    Home

    Submit your QU affiliated work

    Browse

    All of Digital Hub
      Communities & Collections Publication Date Author Title Subject Type Language Publisher
    This Collection
      Publication Date Author Title Subject Type Language Publisher

    My Account

    Login

    Statistics

    View Usage Statistics

    Qatar University Digital Hub is a digital collection operated and maintained by the Qatar University Library and supported by the ITS department

    Contact Us | Send Feedback
    Contact Us | Send Feedback | QU

     

     

    Video