• English
    • العربية
  • العربية
  • Login
  • QU
  • QU Library
  •  Home
  • Communities & Collections
  • About QSpace
    • Vision & Mission
  • Help
    • Item Submission
    • Publisher policies
    • User guides
      • QSpace Browsing
      • QSpace Searching (Simple & Advanced Search)
      • QSpace Item Submission
      • QSpace Glossary
View Item 
  •   Qatar University Digital Hub
  • Qatar University Institutional Repository
  • Academic
  • Faculty Contributions
  • College of Engineering
  • Civil and Environmental Engineering
  • View Item
  • Qatar University Digital Hub
  • Qatar University Institutional Repository
  • Academic
  • Faculty Contributions
  • College of Engineering
  • Civil and Environmental Engineering
  • View Item
  •      
  •  
    JavaScript is disabled for your browser. Some features of this site may not work without it.

    Multiobjective optimization model for scheduling of construction projects under extreme weather

    Thumbnail
    View/Open
    1303-Article Text-2643-1-10-20180414.pdf (1.257Mb)
    Date
    2016
    Author
    Senouci, Ahmed B.
    Mubarak, Saleh A.
    Metadata
    Show full item record
    Abstract
    Extreme weather significantly impacts construction schedules and costs and can be a source of schedule delays and budget overruns. A multi-objective optimization model, presented herein for the scheduling of construction projects under extreme weather conditions, can generate optimal/near optimal schedules that minimize the time and cost of construction projects in extreme weather regions. The model computations are organized as follows: (1) a scheduling module for developing practical schedules for construction projects, (2) a cost module for computing total project cost, and (3) a multi-objective module for determining optimal/near optimal trade-offs between project time and cost. Two practical examples of the effects of extreme weather on construction time and direct cost are provided, the first of which shows the impact of extreme weather on construction time and cost, and the second of which demonstrates the ability of the model to generate and visually present the optimal trade-offs between the duration and costs of construction projects under extreme weather conditions.
    DOI/handle
    http://dx.doi.org/10.3846/13923730.2014.897968
    http://hdl.handle.net/10576/17977
    Collections
    • Civil and Environmental Engineering [‎881‎ items ]

    entitlement


    Qatar University Digital Hub is a digital collection operated and maintained by the Qatar University Library and supported by the ITS department

    Contact Us
    Contact Us | QU

     

     

    Home

    Submit your QU affiliated work

    Browse

    All of Digital Hub
      Communities & Collections Publication Date Author Title Subject Type Language Publisher
    This Collection
      Publication Date Author Title Subject Type Language Publisher

    My Account

    Login

    Statistics

    View Usage Statistics

    About QSpace

    Vision & Mission

    Help

    Item Submission Publisher policies

    Qatar University Digital Hub is a digital collection operated and maintained by the Qatar University Library and supported by the ITS department

    Contact Us
    Contact Us | QU

     

     

    Video